Stage Should Be Poured Next Week For New TVHS Auditorium

Shown is a view of Tippecanoe Valley High School’s new auditorium’s stage area.
Text and Photos
By Leah Sander
InkFreeNews

AKRON — Workers should pour the new Tippecanoe Valley High School auditorium stage next week.

At its monthly public work session on Thursday, May 16, the Tippecanoe Valley School Board heard that information from The Skillman Corp. Project Manager Scott Rogers. The Skillman Corp. is the construction management company for TVHS’ ongoing construction project, of which the auditorium is part.

Other plans for the next month in the auditorium are to finish bricking the stage wall and begin work on light fixtures and reflector ceilings.

For the new agriculture area, the construction crew worked on walls over the last month, which they will drywall and paint over the next month.

As for the pool, it was tested for leaks in the last month, with workers to install tile in the pool tank over the next month.

All work is estimated to be done around September.

The welding section of TVHS’ new agriculture shop is shown.